Capital Improvement Plan · Q2-26

Capital projects across Harborview

Ten active capital projects — from the Municipal Pier rehabilitation to the Compass Point Road widening. The map shows each project corridor colored by status; open a project for its budget, phase schedule, and description.

Active Projects

10

Total Budget

$50.85M

Expended to Date

$16.86M (33.15%)

Project Map

Corridors colored by project status — click to highlight

Projects

Budget and expenditures as reported in Q2-26

BG10

Harborview Maritime Museum

Planning & Design
On Target

Schedule

Jan 2026 – Apr 2027

% Complete

25%

Budget

$6.4M

Expended

$1.18M (18.44%)
The Town of Harborview is developing a new Maritime Museum to celebrate the community’s port heritage and attract regional tourism. The facility will include exhibit galleries, a community event space, and waterfront viewing areas. The project is funded through a combination of general fund reserves and a state cultural grant.
1500 SE 17th St, Fort Lauderdale, FL 33316

Progress photo · Q2-26

BG14

Fire Station No. 3

Construction
On Target

Schedule

Jun 2024 – Dec 2026

% Complete

40%

Budget

$9.75M

Expended

$5.23M (53.64%)
This project delivers a new fire station to serve Harborview’s growing eastern district, reducing emergency response times for residents and businesses. The facility includes three apparatus bays, living quarters, and training space. Funding is provided through a public safety bond approved by voters.
2801 NW 9th Ave, Fort Lauderdale, FL 33311

Progress photo · Q2-26

IF05

Port Access Road Utilities

Pre-Construction
Caution

Schedule

Feb 2025 – Oct 2026

% Complete

65%

Budget

$3.9M

Expended

$1.72M (44.10%)
The Town is upgrading water and sewer utilities along the primary port access corridor to support increased freight traffic and planned commercial development. Utility relocation work has caused intermittent lane closures. The project is funded through utility enterprise funds and a state infrastructure grant.
1850 Eller Dr, Fort Lauderdale, FL 33316

Progress photo · Q2-26

IF09

Seagrove District Infrastructure

ROW Acquisition
No Information

Schedule

Apr 2026 – Jul 2027

% Complete

15%

Budget

$5.25M

Expended

$410K (7.81%)
This project constructs public infrastructure to support the future Seagrove mixed-use district, including roadway, drainage, and utility extensions. The district is expected to bring new retail, dining, and residential development to Harborview. The Town anticipates increased property and sales tax revenue upon completion.
600 Seabreeze Blvd, Fort Lauderdale, FL 33316

Progress photo · Q2-26

RW03

Bayshore Drive Reconstruction

Construction
On Target

Schedule

Jan 2024 – Oct 2026

% Complete

55%

Budget

$4.8M

Expended

$4.61M (96.04%)
Bayshore Drive is being fully reconstructed to address pavement failure and improve stormwater drainage along the corridor. Unforeseen subsurface utility conflicts have caused cost overruns and construction delays. The project remains a Town priority given its role as a primary connector to the waterfront district.
3001 Bayshore Dr, Fort Lauderdale, FL 33304

Progress photo · Q2-26

RW11

Compass Point Road Widening

Planning & Design
Below Plan

Schedule

May 2026 – Apr 2028

% Complete

10%

Budget

$7.1M

Expended

$95K (1.34%)
This project will widen Compass Point Road from two to four lanes to accommodate growing traffic volumes from nearby residential development. Planning includes traffic modeling, environmental review, and preliminary design. The project is funded through a combination of impact fees and a transportation bond.
4201 N Federal Hwy, Fort Lauderdale, FL 33308

Progress photo · Q2-26

SW02

Tidewater Lift Station Upgrade

Bid
On Target

Schedule

Mar 2026 – Jan 2027

% Complete

31%

Budget

$2.65M

Expended

$875K (33.02%)
The Town is upgrading the aging Tidewater lift station to increase capacity and reliability for the surrounding service area. The upgrade will reduce the risk of sanitary sewer overflows during peak flow events. The project is funded through the wastewater utility capital improvement budget.
1200 SW 4th Ave, Fort Lauderdale, FL 33315

Progress photo · Q2-26

SW07

Harbor Creek Drainage Improvements

Pre-Construction
Caution

Schedule

Jun 2026 – Oct 2027

% Complete

35%

Budget

$3.3M

Expended

$690K (20.91%)
This project improves stormwater drainage capacity along Harbor Creek to reduce localized flooding during heavy rain events. Work includes channel widening and culvert replacement. Nearby residents may experience periodic access restrictions during construction staging.
1501 NE 26th St, Fort Lauderdale, FL 33305

Progress photo · Q2-26

PK04

Pelican Bay Waterfront Park

Closeout
On Target

Schedule

Jan 2023 – Oct 2025

% Complete

70%

Budget

$2.1M

Expended

$2.05M (97.40%)
This project delivered a new waterfront park along Pelican Bay, including a promenade, shade pavilions, and native landscaping. The park supports the Town’s waterfront revitalization strategy and is expected to increase tourism visits and adjacent commercial activity.
3000 E Sunrise Blvd, Fort Lauderdale, FL 33304

Progress photo · Q2-26

PT06

Municipal Pier Rehabilitation

Planning & Design
On Target

Schedule

Jan 2026 – Dec 2026

% Complete

90%

Budget

$5.6M

Expended

$0 (0.00%)
The Town of Harborview is rehabilitating the aging municipal pier to address structural deterioration and extend its service life. The project will replace decking, pilings, and lighting while preserving public fishing and recreational access. Funding is anticipated through a mix of general fund reserves and a state resilience grant.
200 S Fort Lauderdale Beach Blvd, Fort Lauderdale, FL 33316

Progress photo · Q2-26